CB Construction (Cleveland) fabricated and supplied the CP Frame for the project at Tilbury Docks, London. We took the project from the client’s initial model through detailing, fabrication and finishing to delivery, including an escorted 4.9 m-wide load.
From model to fabrication
Working from the model supplied by the client, our detailing team produced the fabrication drawing package. We sourced the materials, fabricated the steelwork and fully assembled the components in our workshop.
Painting, flooring and final QA
Following fabrication and assembly, the frames were blast-cleaned and painted. We then fitted the flooring and carried out quality checks before dispatch.
Delivery to Tilbury Docks
We coordinated the transport of the steelwork to Tilbury Docks. One frame measured 4.9 m wide and travelled as an escorted abnormal load. The client carried out the erection on site.